The Everett M&I Metrics screen, Figure 5.16, provides
information about Everett M&I demands and supply reliability over the period
of simulation.

Figure 5.16
Everett M&I Metrics
|
Navigation Buttons: |
|
|
Information Screens |
|
| |
Everett Documentation |
|
Input Screens: |
|
| |
Everett Control Panel |
| |
Regional Control Panel |
|
Output Screens: |
|
| |
Jackson Power |
| |
Lake Chaplain |
| |
Spada Reservoir |
| |
Sultan River Metrics |
| |
Sultan River Metrics, Continued |
|
Output Information: |
|
|
Annual M&I Reliability |
Percentage of M&I failures
over total model run. |
|
M&I Failure Years |
This field presents the number
of years during which there was at least one M&I failure. |
|
Total Shortfall Volume |
Total volume, in acre-feet, not
delivered |
|
Total Weeks Failure |
This field presents the total
number of weeks during which there was a shortfall. |
|
Year of Investigation |
This field displays the Year of
Investigation entered into the Regional Control Panel. |
|
Graph: |
|
|
Final Demand |
This graph illustrates the
weekly M&I demand for Everett, in mgd. |